1. Purpose

This document defines the Standard Operating Procedures (SOPs) and data upload guidelines to be followed by Programme Teams while preparing and uploading data for the Microplanning module. Adherence to these SOPs ensures data consistency, accuracy, and successful ingestion into the system.


2. Scope

This SOP applies to all Programme Team members responsible for preparing, validating, and uploading boundary and geographic data required for microplanning activities.


3. Roles and Responsibilities

  • Programme Teams: Prepare data files as per prescribed formats and guidelines.

  • System Administrators: Provide training on naming conventions and oversee data readiness.

  • Implementation Support Teams: Assist with validation errors and troubleshooting, if required.


4. Supported Input Formats

The Microplanning module supports the following input formats:

  • Pre-defined Excel template

  • GeoJSON files (pre-defined schema)

  • Shapefile (zipped)

Only the supported formats listed above will be accepted by the system.


5. Data Upload SOP

5.1 Boundary-wise Data Configuration

  • Data must be configured starting from Admin Level 0.

  • Uploads must follow a one-file-per-boundary rule:

    • One file for all Admin 0 boundaries

    • One file for each Admin 1 boundary

5.2 Naming Convention

  • A standard naming convention must be followed for all uploaded files.

  • Training on naming conventions will be provided by the system administrators.

  • Files not adhering to the agreed naming convention may be rejected.


6. Input File Validation Guidelines

6.1 GeoJSON Validation Rules

All GeoJSON files must comply with the following rules:

  • Must conform to RFC 7946 GeoJSON specification

  • The top-level element must be of type FeatureCollection

  • All features must have geometries of the same type (e.g., all Points or all MultiPolygons)

  • Coordinates must be within valid ranges:

    • Latitude: -90 to +90

    • Longitude: -180 to +180

  • Any third coordinate (height value), if present, will be ignored

  • All features must contain properties with the same set of keys

  • Numeric values must not be quoted in the properties object

    • Example: "population": 10000 (valid)

    • Example: "population": "10,000" (invalid)


6.2 Shapefile Validation Rules

Shapefile uploads must meet the following requirements:

  • A valid shapefile must include, at a minimum:

    • .shp, .shx, and .dbf files

  • Optional supporting files may include:

    • .prj, .sbx, .sbn

  • All files must be compressed and uploaded in ZIP format

  • Coordinate reference system must be WGS 84 (EPSG:4326)

    • If .prj is missing, WGS 84 is assumed

    • Any other coordinate system is not supported

  • Coordinates must be within valid ranges:

    • Latitude: -90 to +90

    • Longitude: -180 to +180

  • Field names must not exceed 10 characters, as per shapefile specifications

  • Attribute fields must use appropriate data types:

    • Numeric values must be stored as Integer, Float, or Double fields

  • Total size of all zipped files must not exceed 2 GB


6.3 Excel Validation Rules

When using the Excel upload template, ensure the following:

  • Latitude and Longitude values must be in:

    • Degree Decimal (e.g., 12.3455), or

    • Degree Minute Seconds (DMS) format without symbols

  • Symbol-based formats are not supported

    • Example: 12° 20' 43.7994" (invalid)

  • All leading and trailing whitespace characters will be automatically stripped, including:

    • Spaces

    • Tabs

    • Carriage returns

    • New lines


7. Compliance and Enforcement

  • All uploaded data is subject to system validation checks.

  • Files failing validation will be rejected and must be corrected before re-upload.

  • Repeated non-compliance may delay microplan setup and campaign timelines.


8. Versioning and Updates

This SOP is applicable for Microplanning Module v0.1. Any updates or changes to supported formats or validation rules will be communicated separately and reflected in updated versions of this document.


9. Support

For questions or support related to data preparation or upload issues, Programme Teams should contact the designated system administrator or implementation support team.

Last updated

Was this helpful?