Document Verifier (DV)

The Document Verifier (DV) is responsible for verifying the required and supporting documents uploaded by the citizen or the stakeholder with the building permit or occupancy certificate application. The application is forwarded to the Field Inspector for further review once the DV finds the documents uploaded meet the requirements. Else, the application is either sent back to the citizen for refurbishing the documents or rejected.

DV can

Field Inspector (FI)

The field inspector or FI is responsible for conducting the field inspection of the construction site and premises. The FI prepares the inspection report based on the observations of the defined inspection parameters.

The FI can -

NOC Verifier

The NOC Verifier is responsible for checking the no-objection permissions obtained for various civic authorities in the context of the building construction. Commonly, a NOC is required from the Airports Authority and the Fire department to certify all guidelines are met by the builder and owner. If all requirements are met the NOC verifier forwards the application to the BPA Approver.

NOC Verifier can

BPA Approver

The BPA Approver is responsible for approving or rejecting the application for building permits or occupancy certificates. Once approved the owner can download the permit or the occupancy certificate from the portal.

The BPA Approver can