# Implementation Plan

| Task                                                                             | Owner                                                | Assigned To                     | Dependency                                                                                | Effort Estimation (Days) | Start Date  | End Date    | Revised Start Date | Revised End Date | New End Date | Status      | Comments                                                                                                                                    |                                                                                       |
| -------------------------------------------------------------------------------- | ---------------------------------------------------- | ------------------------------- | ----------------------------------------------------------------------------------------- | ------------------------ | ----------- | ----------- | ------------------ | ---------------- | ------------ | ----------- | ------------------------------------------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------- |
| Handover of FSM1.3                                                               | Riddhi                                               | Taresh, Rakesh, Venu and Taniya |                                                                                           |                          | 20-Mar-2023 | 20-Mar-2023 | 29-Mar-2023        | 29-Mar-2023      |              | Completed   | Communication to the team with the docs of FSMv1.3                                                                                          |                                                                                       |
| Master data validation for 37 new ULBs                                           | Riddhi                                               | Taresh and Taniya               |                                                                                           | 4                        | 1-Mar-2023  | 17-Mar-2023 | 1-Mar-2023         | 24-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Setting up of master data and configurations on FSM test server                  | Riddhi                                               | Taresh and Taniya               |                                                                                           | 1.5                      | 20-Mar-2023 | 21-Mar-2023 | 23-Mar-2023        | 24-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Deployment of new version(FSM1.3) in FSM test environment                        | Riddhi                                               | Taresh                          |                                                                                           | 0.5                      | 20-Mar-2023 | 21-Mar-2023 | 23-Mar-2023        | 24-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Listing the changes in core services related to FSM1.3                           | Riddhi                                               | Taresh                          |                                                                                           | 0.5                      | 21-Mar-2023 | 22-Mar-2023 | 30-Mar-2023        | 30-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Taking the core service changes(if any) with PwC team and getting their approval | Riddhi                                               | Taresh                          |                                                                                           | 0.5                      | 22-Mar-2023 | 23-Mar-2023 | 31-Mar-2023        | 31-Mar-2023      |              | NA          | I am told there are no such changes. If that is the case mark the status as NA.                                                             |                                                                                       |
| QA sign off on FSM test server                                                   | Riddhi                                               | Venu                            |                                                                                           | 2                        | 23-Mar-2023 | 24-Mar-2023 | 2-Apr-2023         | 17-Apr-2023      | 18-Apr-2023  | Completed   |                                                                                                                                             |                                                                                       |
| URC & E2E Testing - QA Sign Off                                                  | Riddhi                                               | Venu                            |                                                                                           | 2                        |             |             | 5-Apr-2023         | 17-Apr-2023      | 19-Apr-2023  | Completed   |                                                                                                                                             |                                                                                       |
| Sign Off from the Program Team                                                   | Riddhi/Arindam/Shrija/Abhishek                       | Shrija, Abhishek, Pradeep       |                                                                                           | 2                        | 27-Mar-2023 | 27-Mar-2023 | 11-Apr-2023        | 17-Apr-2023      |              | In-Progress |                                                                                                                                             |                                                                                       |
| Customization suggested by Program team                                          | Riddhi/Arindam                                       | Rakesh/Taresh                   |                                                                                           | 2                        | 28-Mar-2023 | 29-Mar-2023 | 4-Apr-2023         | 17-Apr-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Core service code merge(if any) on SUJOG UAT by PwC                              | Riddhi/Arindam                                       | Rakesh/Taresh                   | NA                                                                                        | 0.5                      | 29-Mar-2023 | 29-Mar-2023 | 14-Apr-2023        | 17-Apr-2023      | NA           | NA          | This is not applicable in the case of V1.3.                                                                                                 |                                                                                       |
| Sujog UAT set up with lastest builds and master data                             | Riddhi/Arindam                                       | Taresh, Taniya and Rakesh       | DATA COLLECTION HAS TO BE COMPLETE                                                        | 3                        | 30-Mar-2023 | 3-Apr-2023  | 14-Apr-2023        | 18-Apr-2023      | 20-Apr-2023  | Completed   | Align with the PwC on the deployment. There are MDMS restarts etc which need their approval.                                                |                                                                                       |
| QA sign off on Sujog UAT instance                                                | Riddhi/Arindam                                       | Venu, Riddhi and Arindam        | Check with Taresh on whether MDMS change will be tested by PwC and how manys do they need | 2                        | 4-Apr-2023  | 5-Apr-2023  | 18-Apr-2023        | 20-Apr-2023      | 3-May-2023   | Completed   | Need the approval from PwC                                                                                                                  | PR merge from the PwC team is delayed by a 2 days due to the production release issue |
| UAT sign off                                                                     | Riddhi/Arindam/Shrija/Abhishek/Some ULB's in Phase-1 | Shrija, Abhishek, Pradeep       |                                                                                           | 2                        | 6-Apr-2023  | 10-Apr-2023 | 20-Apr-2023        | 21-Apr-2023      | 23-May-2023  | In-Progress | This includes PwC team approval that the testing of SUJOG modules are done on UAT                                                           |                                                                                       |
| Setting up of master data and configurations on production(Specific to FSM1.3)   | Riddhi/Arindam                                       | Taresh and Taniya               |                                                                                           | 3                        | 11-Apr-2023 | 13-Apr-2023 | 24-Apr-2023        | 26-Apr-2023      | 23-May-2023  | Completed   |                                                                                                                                             |                                                                                       |
| Deploying to production                                                          | Riddhi/Arindam                                       | Riddhi/Arindam                  |                                                                                           | 1                        | 11-Apr-2023 | 13-Apr-2023 | 26-Apr-2023        | 26-Apr-2023      | 26-May-2023  | Completed   | Email communication to PwC team                                                                                                             |                                                                                       |
| Sanity testing on production using testing tenant                                | Riddhi/Arindam                                       | Venu, Riddhi, Arindam, Abhisekh |                                                                                           | 1                        | 14-Apr-2023 | 17-Apr-2023 | 26-Apr-2023        | 26-Apr-2023      | 24-May-2023  | Completed   | After this stage, we can announce to all existing ULBs on the v1.3 upgrade. Ideally, items 18 and 19 should happen within the same evening. |                                                                                       |
| Setting up of new ULB's, Master data, Seed data, User creations for 37 ULB's     | Riddhi/Arindam                                       | Taresh, Taniya, Venu            |                                                                                           | 12                       | 14-Apr-2023 | 19-Apr-2023 | 10-Apr-2023        | 28-Apr-2023      | 7-Jun-2023   | In-Progress |                                                                                                                                             |                                                                                       |
| Release communication                                                            | Riddhi/Arindam                                       | Riddhi/Arindam                  |                                                                                           |                          | 19-Apr-2023 | 19-Apr-2023 | 28-Apr-2023        | 28-Apr-2023      | 7-Jun-2023   | To Do       | Email communication about the new ULBs made live                                                                                            |                                                                                       |


---

# Agent Instructions: Querying This Documentation

If you need additional information that is not directly available in this page, you can query the documentation dynamically by asking a question.

Perform an HTTP GET request on the current page URL with the `ask` query parameter:

```
GET https://docs.digit.org/sanitation/reference-implementations/odisha-sujog/implementation-plan.md?ask=<question>
```

The question should be specific, self-contained, and written in natural language.
The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.