# Implementation Plan

| Task                                                                             | Owner                                                | Assigned To                     | Dependency                                                                                | Effort Estimation (Days) | Start Date  | End Date    | Revised Start Date | Revised End Date | New End Date | Status      | Comments                                                                                                                                    |                                                                                       |
| -------------------------------------------------------------------------------- | ---------------------------------------------------- | ------------------------------- | ----------------------------------------------------------------------------------------- | ------------------------ | ----------- | ----------- | ------------------ | ---------------- | ------------ | ----------- | ------------------------------------------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------- |
| Handover of FSM1.3                                                               | Riddhi                                               | Taresh, Rakesh, Venu and Taniya |                                                                                           |                          | 20-Mar-2023 | 20-Mar-2023 | 29-Mar-2023        | 29-Mar-2023      |              | Completed   | Communication to the team with the docs of FSMv1.3                                                                                          |                                                                                       |
| Master data validation for 37 new ULBs                                           | Riddhi                                               | Taresh and Taniya               |                                                                                           | 4                        | 1-Mar-2023  | 17-Mar-2023 | 1-Mar-2023         | 24-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Setting up of master data and configurations on FSM test server                  | Riddhi                                               | Taresh and Taniya               |                                                                                           | 1.5                      | 20-Mar-2023 | 21-Mar-2023 | 23-Mar-2023        | 24-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Deployment of new version(FSM1.3) in FSM test environment                        | Riddhi                                               | Taresh                          |                                                                                           | 0.5                      | 20-Mar-2023 | 21-Mar-2023 | 23-Mar-2023        | 24-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Listing the changes in core services related to FSM1.3                           | Riddhi                                               | Taresh                          |                                                                                           | 0.5                      | 21-Mar-2023 | 22-Mar-2023 | 30-Mar-2023        | 30-Mar-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Taking the core service changes(if any) with PwC team and getting their approval | Riddhi                                               | Taresh                          |                                                                                           | 0.5                      | 22-Mar-2023 | 23-Mar-2023 | 31-Mar-2023        | 31-Mar-2023      |              | NA          | I am told there are no such changes. If that is the case mark the status as NA.                                                             |                                                                                       |
| QA sign off on FSM test server                                                   | Riddhi                                               | Venu                            |                                                                                           | 2                        | 23-Mar-2023 | 24-Mar-2023 | 2-Apr-2023         | 17-Apr-2023      | 18-Apr-2023  | Completed   |                                                                                                                                             |                                                                                       |
| URC & E2E Testing - QA Sign Off                                                  | Riddhi                                               | Venu                            |                                                                                           | 2                        |             |             | 5-Apr-2023         | 17-Apr-2023      | 19-Apr-2023  | Completed   |                                                                                                                                             |                                                                                       |
| Sign Off from the Program Team                                                   | Riddhi/Arindam/Shrija/Abhishek                       | Shrija, Abhishek, Pradeep       |                                                                                           | 2                        | 27-Mar-2023 | 27-Mar-2023 | 11-Apr-2023        | 17-Apr-2023      |              | In-Progress |                                                                                                                                             |                                                                                       |
| Customization suggested by Program team                                          | Riddhi/Arindam                                       | Rakesh/Taresh                   |                                                                                           | 2                        | 28-Mar-2023 | 29-Mar-2023 | 4-Apr-2023         | 17-Apr-2023      |              | Completed   |                                                                                                                                             |                                                                                       |
| Core service code merge(if any) on SUJOG UAT by PwC                              | Riddhi/Arindam                                       | Rakesh/Taresh                   | NA                                                                                        | 0.5                      | 29-Mar-2023 | 29-Mar-2023 | 14-Apr-2023        | 17-Apr-2023      | NA           | NA          | This is not applicable in the case of V1.3.                                                                                                 |                                                                                       |
| Sujog UAT set up with lastest builds and master data                             | Riddhi/Arindam                                       | Taresh, Taniya and Rakesh       | DATA COLLECTION HAS TO BE COMPLETE                                                        | 3                        | 30-Mar-2023 | 3-Apr-2023  | 14-Apr-2023        | 18-Apr-2023      | 20-Apr-2023  | Completed   | Align with the PwC on the deployment. There are MDMS restarts etc which need their approval.                                                |                                                                                       |
| QA sign off on Sujog UAT instance                                                | Riddhi/Arindam                                       | Venu, Riddhi and Arindam        | Check with Taresh on whether MDMS change will be tested by PwC and how manys do they need | 2                        | 4-Apr-2023  | 5-Apr-2023  | 18-Apr-2023        | 20-Apr-2023      | 3-May-2023   | Completed   | Need the approval from PwC                                                                                                                  | PR merge from the PwC team is delayed by a 2 days due to the production release issue |
| UAT sign off                                                                     | Riddhi/Arindam/Shrija/Abhishek/Some ULB's in Phase-1 | Shrija, Abhishek, Pradeep       |                                                                                           | 2                        | 6-Apr-2023  | 10-Apr-2023 | 20-Apr-2023        | 21-Apr-2023      | 23-May-2023  | In-Progress | This includes PwC team approval that the testing of SUJOG modules are done on UAT                                                           |                                                                                       |
| Setting up of master data and configurations on production(Specific to FSM1.3)   | Riddhi/Arindam                                       | Taresh and Taniya               |                                                                                           | 3                        | 11-Apr-2023 | 13-Apr-2023 | 24-Apr-2023        | 26-Apr-2023      | 23-May-2023  | Completed   |                                                                                                                                             |                                                                                       |
| Deploying to production                                                          | Riddhi/Arindam                                       | Riddhi/Arindam                  |                                                                                           | 1                        | 11-Apr-2023 | 13-Apr-2023 | 26-Apr-2023        | 26-Apr-2023      | 26-May-2023  | Completed   | Email communication to PwC team                                                                                                             |                                                                                       |
| Sanity testing on production using testing tenant                                | Riddhi/Arindam                                       | Venu, Riddhi, Arindam, Abhisekh |                                                                                           | 1                        | 14-Apr-2023 | 17-Apr-2023 | 26-Apr-2023        | 26-Apr-2023      | 24-May-2023  | Completed   | After this stage, we can announce to all existing ULBs on the v1.3 upgrade. Ideally, items 18 and 19 should happen within the same evening. |                                                                                       |
| Setting up of new ULB's, Master data, Seed data, User creations for 37 ULB's     | Riddhi/Arindam                                       | Taresh, Taniya, Venu            |                                                                                           | 12                       | 14-Apr-2023 | 19-Apr-2023 | 10-Apr-2023        | 28-Apr-2023      | 7-Jun-2023   | In-Progress |                                                                                                                                             |                                                                                       |
| Release communication                                                            | Riddhi/Arindam                                       | Riddhi/Arindam                  |                                                                                           |                          | 19-Apr-2023 | 19-Apr-2023 | 28-Apr-2023        | 28-Apr-2023      | 7-Jun-2023   | To Do       | Email communication about the new ULBs made live                                                                                            |                                                                                       |