Validate & Approve Microplan Estimation

Overview

The Microplan Estimation Approver screen allows supervisors to validate and approve microplan estimations within their assigned administrative boundaries. This screen enables approvers to validate, correct, and approve data, ensuring the integrity of the data used for resource planning.

User Roles

Roles
Description
Role Code

Plan Estimation Approver

Responsible for validating the estimation data, ensuring its accuracy, including the ability to edit data, approve, or send data back for correction.

PLAN_ESTIMATION_APPROVER

Root Plan Estimation Approver

Responsible for validating the estimation data, ensuring its accuracy, including the ability to edit data, approve, or send data back for correction. Has additional permissions, including the ability to finalise microplan estimation data.

ROOT_PLAN_ESTIMATION_APPROVER

Interface Elements

Header Section

  • Microplan Name: Displays the name of the current microplan being reviewed.

  • Logged-in User: Indicates the user role and account.

Plan Estimation Data Summary (KPIs)

  • All values are dynamically updated based on the real-time plan data.

  • These values are sourced directly from microplan-specific KPIs, which reflect any actions taken by data approvers.

  • The values will change accordingly as the plan estimation data is reviewed, corrected, or approved.

Search and Filters:

Search

  • Administrative Hierarchy and Area Selection: Dropdown menus for selecting specific administrative areas (e.g., district and village).

Filters

  • Filter Options:

    • Workflow Status Filters:

      • Pending validation

      • Validated

      • Assigned to Filters:

        • Assigned to me

        • Assigned to all

    • Road Condition Filters:

      • Filter based on the condition of the road (no road, gravel, dirt)

    • Terrain Filters:

      • Filter based on terrain (forest, mountain, plain, desert)

    • Security Questions:

      • Based on the security level, filters can be applied

    • Facility Filters:

      • Filters village based on the facility, when applied, gives all the villages assigned to that facility

    Options for Filters

    • Accessibility Filters:

      • Options are retrieved from MDMS v2 using the useCustomMdms hook.

      • The MDMS v2 returns a JSON object containing accessibility and other related information.

      • The schema code used is ['hcm-microplanning'] with the masters, including onRoadCondition, terrain, and securityQuestions.

    • Facility Options:

      • Retrieved from plan-service/plan/facility/_search

      • Buttons: Apply Filter, Clear

Purpose
Endpoint
Method
Payload

Options for Facility Filters

/plan-service/plan/facility/_search

POST

{PlanFacilitySearchCriteria: { tenantId: tenantId, planConfigurationId: microplanId, } }

Filter for Accessibility and Facility: Includes Road Condition, Terrain, Security Questions

/plan-serivce/plan/_search

{ "PlanSearchCriteria": { "tenantId": "mz", "active": true, "assignee": "29681317-e282-44da-8d0a-233cc74a3d6d", "facilityId": "F-2024-11-12-068806", "jurisdiction": ["MICROPLAN_MO_13_GRAND_GEDEH"], "onRoadCondition": "HCM_MICROPLAN_CONCRETE", "planConfigurationId": "eb5998fc-024f-4623-a969-3763ec5a8840", "securityQ1": "OFTEN", "securityQ2": "EVERYDAY1", "status": "PENDING_FOR_VALIDATION", "terrain": "HCM_MICROPLAN_FOREST" } }

Plan Estimation Data Table

The table on the Microplan estimation validation page displays key data for each village involved in the campaign, including the village name, status logs, assignee details, and facility name. It also includes important information such as road conditions, terrain, and security factors, which help assess the village’s readiness for planned activities. Additionally, the table presents validated population data, the number of households(based on the selected campaign), and other critical metrics related to the plan data, ensuring that approvers have a comprehensive view of the plan estimation details before approval.

Action Buttons

  • View Logs: Displays historical changes and logs related to a specific plan estimation's data.


Steps

Role-Based Permissions and Actions

Plan Estimation Approver

The Estimation Data Approver is responsible for validating plan data. Their responsibilities include:

Validating Data:

  • Cross-check the uploaded data with the confirmed population to ensure accuracy.

Identifying Discrepancies:

  • If discrepancies are found, the PEA can flag the data for revision.

Approval Workflow:

  • The PDA at the appropriate level will see the application as pending approval. In such cases, the PDA can validate and approve the data.

When No Data Is Assigned:

  • If no data is assigned to the PEA or all data assigned to him is validated, a 'Back' button is shown, allowing them to return to the previous screen.


Root Plan Estimation Approver (RPEA)

The Root Plan Estimation Approver has all the functionalities of a Plan Estimation Approver and additional capabilities, such as finalising the microplan. Their responsibilities include:

Approving or Sending Data for Correction:

  • Once the plan data is validated, the RPEA can either approve it or send it back for correction if further issues are identified.

Approval Workflow:

  • If someone from the hierarchy below modifies and sends the data for approval, the RPEA can approve it. For example, if a province-level user sends the data back to a district-level user, who updates and sends it back for approval, the province-level RPEA will receive the application for approval.

Finalising Actions:

  • If all the villages within the selected microplan have been validated and no further changes are required, the RPDA will see a "Finalise Actions" button at the footer of the page.

  • After finalising the plan data, a success screen will be shown, indicating that the microplan is finalised.

  • The "Finalise Actions" button will lock the data and prevent further modifications once clicked, marking the end of the validation process for the selected microplan or district.

circle-info

Additional Notes

  • Once the plan estimation data reaches the national-level data approver and the validation is finalised, the system will disable all action buttons. The status will be set to "ESTIMATION_APPROVED" and no further changes can be made. At this point, you can download the microplan estimation.

  • Estimation supervisors will only see the boundaries in their inbox that fall under their jurisdiction.

API Endpoints

Purpose
Endpoint
Method
Payload

Fetch plan configuration details

/plan-service/config/_search

POST

{"PlanConfigurationSearchCriteria":{"tenantId":"mz","id":"0dfe322d-727c-489f-a5a8-e8b7a0a43cc4"}}

Fetch project types for a campaign

/project-factory/v1/project-type/search

POST

{"CampaignDetails":{"tenantId":"mz","ids":["fede1b71-464d-48be-a2ab-c27147df42c4"]}}

Search for assigned employees

/plan-service/employee/_search

POST

{"PlanEmployeeAssignmentSearchCriteria":{"tenantId":"mz","active":true,"planConfigurationId":"0dfe322d-727c-489f-a5a8-e8b7a0a43cc4","role":["PLAN_ESTIMATION_APPROVER","ROOT_PLAN_ESTIMATION_APPROVER"],"employeeId":["d3b6f2fb-97b7-4103-aa47-e03f0ba47b18"],"limit":5,"offset":0}}

Fetch workflow process details

/egov-workflow-v2/egov-wf/process/_search

POST

SearchParams{

tenantId=mz,

history=true,

businessIds=275135ab-2c22-48aa-8325-88f42c4d29ce

}

Search for plans by configuration

/plan-service/plan/_search

POST

{"PlanSearchCriteria":{"tenantId":"mz","planConfigurationId":"0dfe322d-727c-489f-a5a8-e8b7a0a43cc4"}}