Program Roll Out Plan
DIGIT Urban 2.9 release has a new following features:
DIGIT Urban 2.9 Beta Features
DIGIT as a Service
Bug Fixes
Task | Status | Owner |
---|---|---|
Upgrade of UPYOG with Beta features | 15/05/2023 | Pradeep Kumar |
Session with NUDM team on Central Instance | 31/07/2023 | Ajay Rawat |
Getting approval from partners for UPYOG upgrade with DIGIT as a Service | In Progress | Ajay Rawat |
Effort Estimate for Upgrade created | Done | Vinoth |
Gate 2 | In Progress | Ajay Rawat |
Release Communication Shared with Partners | To Do | Ajay Rawat |
NUDM Roll Out
NUDM Team has shared following requirements for upgrading UPYOG with Central Instance:
*Conditions for Upgrading UPYOG with Central Instance
Role & Access Management at Cluster Level so that each State SI is able to do its scope of work
Role & Access Management at Logs Level so that each State SI is able to do its scope of work
Role & Access Management at Elastic Search & Kibana Level so that each State SI is able to do its scope of work
Enhancement & verification of Product default Kafka with more nodes, partitions, etc so that it sustains and perform for National Level traffic
Enhancement & verification of Product default ElasticSearch with more nodes, shards, etc so that it sustains and perform for National Level traffic
Availability of all States data in its own DB schemas and same should apply with ElasticSearch
Others enhancements so that State Infra & DevOps team should be able to manage their resources independently
Adoption Metrics
Citizen Feedback | No. of states adopting feature and sharing data with National Dashboard | At least 2 states to implement the feature under NUDM in next 6 months |
Consent form | Compliance to NUIS Assessment | Compliance report already shared post release of feature |
Dashboard KPIs | No. of states sharing data on new KPIs | Citizen Feedback feature to be implemented in states, for KPIs to start reflecting data. 2+ states to implement the feature and share data on the KPIs |
DIGIT as a Service | No. of accounts/projects using feature in all missions | At least 2 accounts use DIGIT as a Service in next 6 months |
Success Metrics
Citizen Feedback | Improvement in Citizen Satisfaction | Improvement in Metrics by 20% in first 3 years in state using the feature |
Consent form | Compliance to NUIS Assessment | Compliance report already shared post release of feature |
Dashboard KPIs | Improvement in Citizen Satisfaction | Improvement in Metrics by 20% in first 3 years in state using the KPIs |
DIGIT as a Service | Optimizing resources for saving in infra costs | Saving to be estimated |